Definition
The Gantt Chart is a project tracking tool that visually summarizes the proposed actions to be performed and their dependencies in terms of the durations. It helps identify the critical path - the longest series of linked tasks that must be completed before the last task.
Examples
Example of a Gantt chart for an improvement project.
Application
Gantt charts are living documents intended to be updated with additional tasks and detail as the project develops.